Nintex-SharePoint 2013
You are here: Installing Nintex for SharePoint > Troubleshoot deployment > Issues > Nintex Live: Multiple Workflow actions run in parallel may take hours to complete

Nintex Live: Multiple Workflow actions run in parallel may take hours to complete

Symptom

Processing takes hours to complete when multiple Workflow actions are run in parallel on different servers in a SharePoint farm topology.

Cause

The Nintex Live Workflow Queue Service has been enabled on two or more servers. As a result, the queue service generates a Live event that slows down processing times.

Resolution

Do not enable the Nintex Live Workflow Queue Service on more than one server in a farm topology.