Run parallel actions

This workflow action runs at least two workflow actions simultaneously.

To use the workflow action:

  • Locate the action in Workflow Actions Toolbox (located on the left hand-side);
    • Click on the Category listings to reveal the actions; OR
    • Search for the action using a keyword.
  • Select the action, drag it onto the design canvas and drop it onto a design pearl.

Alternatively

  • Left-clicking the pearl, mouse-over Insert Action and then the Categories to reveal the actions, click the required action from the list.

To change the settings used by the action:

  • On the action’s title click the down arrow to activate a drop-down
  • Select Configure; OR
  • Double-click the action's icon.

For more information on the other options in the drop-down, please refer to the Getting started with the Nintex Workflow designer.

There is no configuration required for this workflow action. However, it is important to note that the workflow will not continue until all workflow paths have been completed. To run more than two actions at a time, left-click on the action title and select 'Add Branch'. If a branch is left empty the workflow will continue to run.